A breach may support damages without permitting termination. The agreement, materiality, dependent obligations, and required notice determine the next step.

A business relationship stops working.

A vendor repeatedly misses delivery deadlines. A service provider fails to complete essential work. A contractor abandons a project. A commercial partner refuses to perform an agreed obligation.

The other party has not delivered what was promised, but the contract may still have months or years remaining.

Can you simply cancel it?

Under California law, the answer depends on more than whether a breach occurred.

A breach of contract may support a claim for damages without necessarily giving the injured party the right to terminate the agreement.

That distinction matters because a business that improperly ends a contract may expose itself to a claim for breach—even when the other party failed to perform first.

The analysis begins with the contract itself and the significance of the alleged breach.

What Does the Contract Say About Termination?

The first step is to examine the agreement's termination provisions.

Commercial contracts frequently address when a party may end the relationship, what notice must be provided, and whether the defaulting party has an opportunity to correct its failure.

Relevant provisions may include termination for cause, termination for convenience, notice and cure, material breach, default, payment obligations, and dispute resolution.

These provisions serve different purposes.

A termination-for-convenience clause may permit a party to end the relationship without establishing fault, subject to the clause's conditions.

A termination-for-cause provision may require proof of a specified default.

A notice-and-cure provision may require written notice describing the breach and a defined opportunity to remedy it before termination becomes effective.

The language matters.

If the agreement requires notice to a designated address or specifies a particular delivery method, sending an informal email to an ordinary business contact may not satisfy the contractual requirement.

A business should therefore identify the exact contractual basis for termination before announcing that the agreement is over.

What Is a Material Breach Under California Law?

California distinguishes between breaches that justify discharge from further performance and breaches that support damages without ending the contractual relationship.1

In Brown v. Grimes (2011) 192 Cal.App.4th 265, 277–279, the Court of Appeal explained that a material breach of a dependent contractual obligation may excuse the other party’s corresponding performance. Dependency is a separate inquiry from materiality.

The court recognized that materiality generally depends on the importance of the obligation and whether the injured party can still obtain substantial performance.

A missed obligation is more likely to be material when it undermines the essential benefit the parties expected from the agreement.

For example, a vendor's repeated failure to deliver a critical product may present a different issue from an isolated administrative error that can be readily corrected.

But the label placed on the breach does not determine the result.

A party cannot necessarily transform a relatively minor failure into grounds for immediate termination merely by describing it as material.

Whether a breach is sufficiently serious is ordinarily a fact-specific question.

Brown denied additional fees but reversed the repayment award for fees already paid because there had not been a total failure of consideration. Excusing future performance is not necessarily the same as unwinding completed exchanges.1

A California Case Illustrates When Termination May Be Justified

In Sackett v. Spindler (1967) 248 Cal.App.2d 220, the parties entered an agreement involving the purchase of stock in a newspaper business.2

The buyer failed to make substantial payments required under the agreement.

The history included repeated payment defaults, a dishonored final-payment check, extensions, and unreliable assurances. The seller eventually terminated further performance and pursued contract damages.

The Court of Appeal upheld the seller's right to treat the buyer's conduct as a total breach.

The decision emphasized that the distinction between a partial breach and a total breach turns on materiality.

The court considered the significance of the unpaid obligation, the history of nonperformance, and uncertainty surrounding whether the buyer would actually complete the transaction.

The lesson extends beyond stock-purchase agreements.

Repeated failures affecting an essential obligation may justify termination even where the defaulting party continues promising future performance.

But the result depends on the circumstances. A single late payment or minor performance defect does not automatically create the same right.

Not Every Breach Excuses Your Business From Performing

A particularly important distinction arises when the contract contains independent obligations.3

In Colaco v. Cavotec SA (2018) 25 Cal.App.5th 1172, the Court of Appeal considered a dispute arising from the sale of a business.

The seller failed to forward certain customer payments as required by the asset-purchase agreement.

The buyer also failed to make a substantial payment owed under that agreement.

The buyer argued that the seller's misconduct excused its own payment obligation.

The Court of Appeal disagreed.

The contractual duties were independent. The seller's breach did not automatically relieve the buyer of its separate obligation to pay the agreed purchase price.

Both payment obligations remained enforceable, subject to an appropriate offset. The ruling did not eliminate the separate fiduciary-duty and conversion liabilities.

That distinction can be commercially significant.

A business may believe it is justified in withholding payment because the other party failed to satisfy another provision.

But if the obligations are independent, withholding payment may constitute a separate breach.

Before suspending performance, determine whether the obligations are contractually dependent.

What if the Other Party Says It Will Not Perform?

Sometimes the breach occurs before the performance deadline.4

California recognizes anticipatory repudiation, also called anticipatory breach.

In Taylor v. Johnston (1975) 15 Cal.3d 130, the California Supreme Court explained that anticipatory repudiation may occur when a party clearly and unequivocally refuses to perform before performance is due, or engages in conduct that makes substantial performance impossible.

The distinction is important.

A statement expressing concern about meeting a deadline is not necessarily an unequivocal refusal to perform.

Nor does every delay establish repudiation.

But where the evidence demonstrates a sufficiently definite refusal or inability to perform essential contractual obligations, the other party may have remedies before the scheduled performance date.

California's Judicial Council Civil Jury Instruction CACI No. 324 addresses this doctrine. The claimant must also establish that it would have been able to fulfill the contract.5

A business considering action based on anticipatory repudiation should preserve the actual communications and conduct supporting that conclusion.

An ambiguous statement should not be treated as a definitive cancellation without careful evaluation.

Taylor also illustrates the limits of this doctrine: the initial repudiation was retracted, and later scheduling difficulties did not establish renewed repudiation while timely performance remained possible. The Supreme Court reversed the judgment for Taylor.4

Do You Have to Give the Other Party a Chance to Fix the Breach?

That depends on the contract and applicable law.

There is no universal contractual cure period that applies to every California commercial agreement.

Many contracts create their own procedures.

For example, an agreement may require written notice identifying the alleged default and provide a specified period for corrective action.

A party invoking that provision generally must evaluate and comply with the applicable requirements.

Even where the contract does not expressly provide a cure period, allowing an opportunity to resolve a disputed default may sometimes be commercially sensible.

A written notice can identify the relevant obligation, describe the alleged failure, request corrective action, and reserve the notifying party's contractual rights.

But the notice should be carefully framed.

A business should avoid demanding obligations that the agreement does not actually impose or threatening immediate termination without a supportable basis.

The objective is to create a clear record while preserving available remedies.

Termination and Rescission Are Not the Same Thing

Businesses frequently use the terms cancel, terminate, and rescind interchangeably.

California law does not always treat them as equivalent.

Termination generally concerns ending the parties' continuing contractual relationship or future performance obligations.

Rescission is a distinct legal remedy that seeks to unwind the contractual transaction, subject to applicable statutory requirements.

California Civil Code section 1689 identifies circumstances in which a party may rescind a contract, including certain failures of consideration and agreements induced by fraud or mistake.6

Section 1691 generally requires prompt notice and restoration—or an offer to restore—benefits received, subject to statutory qualifications including section 1693. Knowledge of the relevant facts and right to rescind matters; service of a rescission pleading can constitute notice or an offer to restore.7

Section 1692 governs relief following rescission and permits courts to award appropriate restitution and other relief while preventing duplicative recovery. A damages claim is not necessarily inconsistent with rescission, but duplicate or inconsistent recoveries are prohibited.8

These requirements matter when substantial payments or benefits have already been exchanged.

For example, a business seeking to recover an advance payment after failed performance may have different remedies from a business seeking damages while retaining benefits already received.

Rescission should not be assumed to follow automatically from every breach of contract.

Can You Recover Money After Terminating the Agreement?

Potentially.

California Civil Code section 3300 provides the general compensatory-damages framework for breach of contract.9

Recoverable damages ordinarily seek to compensate the injured party for losses proximately caused by the breach or that would likely result from it in the ordinary course of events.

Depending on the agreement and evidence, losses may include additional expenses incurred to obtain substitute performance or other reasonably supported economic harm.

The objective is compensation for a legally recoverable loss—not punishment for the breach.

A business must also establish that the claimed damages were actually caused by the defendant's conduct.

In addition, California's mitigation principles generally prevent recovery for losses the injured party could reasonably have avoided.

CACI No. 358 explains that an injured party is not required to undertake unreasonable or unduly burdensome measures, but avoidable losses may be excluded from recovery. The defendant bears the burden of proving avoidable harm; reasonableness is evaluated under the circumstances existing at the time.5

Reasonable expenses incurred to reduce the harm may themselves be recoverable in appropriate circumstances.

The damages analysis should therefore address both the financial consequences of the breach and the practical steps taken to limit the resulting loss.

What if the Contract Involves the Sale of Goods?

Commercial agreements involving the sale of goods may be governed by California's Commercial Code rather than solely by general contract principles.

Commercial Code section 2610 addresses anticipatory repudiation of sales contracts where the repudiation substantially impairs the contract's value to the other party. The aggrieved party may await performance for a commercially reasonable time, resort to breach remedies, and suspend its own performance.10

Section 2711 provides specified remedies for buyers when sellers fail to deliver or repudiate, or when the buyer rightfully rejects goods or justifiably revokes acceptance. Cancellation concerns the affected goods and reaches the whole agreement when the breach goes to the whole contract.11

Those remedies can include cancellation and recovery of certain payments, subject to the statutory requirements.

Other Commercial Code provisions address seller remedies, substitute purchases, installment contracts, and related issues.

The distinction matters because a contract for goods may have different cancellation and remedial rules from a services agreement.

A business purchasing machinery, inventory, or products should therefore identify the transaction's governing legal framework before relying on a general rule about material breach.

What Evidence Should You Preserve Before Terminating?

A business should assemble a reliable record before taking an irreversible contractual position.

The most important documents will often include the signed agreement and amendments, statements of work, purchase orders, delivery schedules, invoices, payment records, correspondence concerning performance, prior notices, and evidence of the alleged default.

The relevant record may also include internal operational records showing how the breach affected the business.

If delays are involved, document when performance was required, what was delivered, whether deadlines were modified, and whether extensions were granted.

If the other party disputes responsibility, preserve the evidence supporting both the original agreement and the subsequent course of performance.

A clear chronology can help determine whether the alleged breach was material and whether the contractual prerequisites for termination were satisfied.

It can also make settlement negotiations more productive.

What Happens if You Wrongfully Terminate?

Improper termination can create liability.

If the alleged breach was insufficient to justify ending the agreement, or the terminating party failed to comply with required procedures, the other side may contend that the termination itself breached the contract.

That risk can become substantial in long-term service agreements, distribution relationships, licensing arrangements, and other contracts where future performance has significant economic value.

The possibility of wrongful termination is one reason businesses should distinguish among several possible responses:

  • Continuing performance while reserving a damages claim.
  • Demanding correction of the default.
  • Negotiating a modification or agreed termination.
  • Suspending performance where legally justified.
  • Terminating under an enforceable contractual provision.
  • Pursuing rescission where statutory grounds exist.

These options do not necessarily produce the same legal or financial result.

A business should evaluate the available alternatives before selecting one.

How Long Do You Have to Pursue a Breach-of-Contract Claim?

The applicable limitations period depends on the claim.12

Code of Civil Procedure section 337 generally provides four years for actions founded on written contracts.

Section 339 generally provides two years for contractual obligations not founded on a written instrument.

However, different rules can apply to sales-of-goods contracts, rescission claims, certain specialized agreements, and other circumstances.

The accrual date also matters.

A business should not assume that continued negotiations, repeated assurances, or an unresolved request to cure automatically extend the deadline.

The applicable limitations period should be determined independently of the business's decision about whether and when to terminate.

Before You Cancel, Identify the Actual Objective

Termination is a legal decision, but it is also a business decision.

Some businesses primarily want the promised performance.

Others want a refund, compensation for losses, a replacement vendor, or an orderly exit from an unproductive relationship.

Those objectives can call for different strategies.

A dispute involving a replaceable vendor may justify a negotiated transition. A long-term contract involving essential technology, inventory, licensing rights, or customer relationships may require a more careful assessment.

The legal inquiry should address four connected questions:

What obligation was breached?

Does that breach legally justify ending further performance?

What procedures must be followed before termination?

What economic consequences will follow if the termination is challenged?

California law may permit a business to end an agreement after a serious breach.

But the strongest position is one supported by the contract, the governing law, and a documented record—not simply frustration with the other party's performance.

Footnotes

  1. 1.
  2. 2.
  3. 3.
  4. 4.
  5. 5.
  6. 6.
  7. 7.
  8. 8.
  9. 9.
  10. 10.
  11. 11.
  12. 12.

Mahrouyan Law handles these matters directly. Read more about how the firm approaches small business & commercial litigation in California, or discuss your own situation with the firm.

Discuss Your Matter

Mahrouyan Law represents California businesses, founders, vendors, and commercial parties in selected contract disputes, including matters involving nonperformance, payment obligations, termination, negotiation, arbitration, and litigation.

Omeed Mahrouyan, founder of Mahrouyan Law, P.C.
Omeed Mahrouyan
Founder & Principal Attorney
Mahrouyan Law, P.C.
California Bar No. 352171 · State Bar profile

Omeed Mahrouyan is the founder of Mahrouyan Law, P.C., a California firm handling business and commercial litigation, property and cargo damage claims, personal injury, landlord representation, startup transactions, and practical intellectual property matters. Clients work directly with him on strategy, drafting, and case decisions.

More about Omeed Mahrouyan →